Greater Pottsville Area Sewer Authority 401 North Centre Street, P.O. Box 1163 Pottsville, PA 17901 |
Main Treatment Plant Expansion - Project 2004 - 1
![]() |
![]() |
![]() |
General Contractor The Quandel Group, Inc. Harrisburg, PA 17112 |
Electrical Contractor Garden Spot Electrical, Inc. Manheim, PA 17545 |
Mechanical Contractor W. G. Tomko & Sons, Inc. Bressler, PA 15332 |
|
Design Engineer Buchart-Horn, Inc. York, PA 15040 |
Construction Manager ARRO Consulting, Inc. Lancaster, PA 17601 |
Project Update:
Last Updated: September 20, 2007
The project was substantially complete on March 31, 2007.
The following photographs provide an overview of the expanded and upgraded facility.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|